Achievements during 2022-23
Updated as on 18.04.2023
SN. |
Project |
Gr. No. |
Name of the section |
RKM |
TKM |
Commissioning Date |
1 |
SC |
268 |
Washim - Hingoli deccan |
46.3 |
57.6 |
28.06.2022 |
2 |
SC |
263 |
Kalikiri- Thammanagunta |
49.87 |
58.76 |
06.08.2022 |
3 |
SC |
269 |
Khanapur - Latur (Upto Udgir) |
51 |
55.1 |
28.09.2022 |
4 |
SC |
269 |
Khanapur (From Udgir) - Latur |
47.7 |
57.63 |
28.09.2022 |
5 |
SC |
208 |
Manoharabad - Kamareddi |
67.28 |
83.43 |
27.10.2022 |
6 |
SC |
208 |
Gadwal- Mahabubnagar |
72.7 |
82 |
26.11.2022 |
7 |
SC |
246 |
Pangri Road-Ausa Road |
79.47 |
90.27 |
30.11.2022 |
8 |
SC |
267 |
Kosai - Himayatnagar |
82.26 |
96.23 |
29.12.2022 |
9 |
SC |
207 |
Rotegaon - Aurangabad |
61.17 |
77.6 |
30.12.2022 |
10 |
SC |
269 |
Latur Road-Parli Vaijnath |
63.75 |
77.4 |
28.01.2023 |
11 |
SC |
267 |
Parli Vaijnath - Pokharni |
46.3 |
49.5 |
09.02.2023 |
12 |
SC |
246 |
Ausa Road - Latur Road |
50 |
58.36 |
23.02.2023 |
13 |
SC |
268 |
Hingoli Deccan-Purna |
78.5 |
89.25 |
02.03.2023 |
14 |
SC |
208 |
Kamareddy - Nizamabad |
49.81 |
57.2 |
17.03.2023 |
15 |
SC |
208 |
Jankampet - Basar |
22.8 |
26 |
17.03.2023 |
16 |
SC |
267 |
Himayatnagar - Mudkhed |
55.7 |
65.35 |
23.03.2023 |
17 |
SC |
267 |
Pokharni - Parbhani |
15.83 |
15.9 |
23.03.2023 |
18 |
SC |
208 |
Gadwal - Kurnool (Telangana) |
49.95 |
54.8 |
25.03.2023 |
19 |
SC |
208 |
Gadwal - Kurnool (A.P.) |
4 |
4 |
25.03.2023 |
20 |
SC |
207 |
Aurangabad - Dinagaon |
55.4 |
62.9 |
31.03.2023 |
Secunderabad Project Electrification done |
1049.79 |
1219.28 |