Target for NJP project during 2021-22 |
SN
|
Rly
|
Proj.
|
Gr.
|
Section
|
RKM
|
TKM
|
Section
2021-22
|
CRS Target for 2021-22 |
Target Quarter
|
Remarks
|
RKM |
TKM |
1
|
NFR
|
NJP
|
255A
|
Jalapiguri Road(excl)- Gumania Hat (Excl) (60 TKM)
|
0
|
60
|
Jalapiguri Road(excl)- Y Leg connection Cabin, 2nd Line (6 TKM) |
0 |
6 |
Q1 |
Track doubling work in progress. |
Betgara - Gumania Hat (Excl) 2nd line (47 TKM) (NTG) |
0 |
47 |
Q1 |
Track doubling work in progress. PDC: march'21 |
2
|
NFR
|
NJP
|
256
|
New Bongaigaon – Goalpara - Kamakhya
|
175
|
236
|
Dudhnoi - Bamnigaon |
56 |
64 |
Q2 |
Track doubling in progress. 2nd line OHE tender under finalisation at CORE PRYJ. PDC: Qr II |
Bamnigaon -Kamakhya |
47 |
53 |
Q2 |
|
3
|
NFR
|
NJP
|
257
|
Guwahati - Lumding
|
181
|
386
|
Jagi Rd - Hojai (1st Line) |
77 |
82 |
Q4 |
Track doubling in progress. Tr line work in progress. TDC- Qr IV |
Hojai - Lumding |
47 |
119 |
Q4 |
Tr line work awarded in Jan'21. TDC- Qr IV |
4
|
NFR
|
NJP
|
307
|
Chaparmukh-Silghat Town incl Senchoa-Mairabari
|
130
|
139
|
Chaparmukh-Senchoa |
19 |
25 |
Q4 |
Tr line work of Dharamtul TSS in adjacent section in progress. Bebejia TSS Tr line work not yet awarded. TDC- Qr IV. |
Senchoa- Silghat Town |
62 |
63 |
Q4 |
Qr-IV. Senchoa- Mairamari (RKM-49, TKM-51) also to be included. |
|
|
|
|
NJP (Awarded) |
486 |
821 |
|
308 |
459 |
|
|
5 |
NFR |
NJP |
257A |
Jagi Rd - Hojai (2nd Line) (82 TKM) |
0 |
82 |
Jagi Rd - Hojai (2nd Line) (82 TKM) |
0 |
82 |
|
Track doubling in progress. OHE tender under process at CORE PRYJ. |
|
|
|
|
NJP (Not awarded) |
0 |
82 |
|
0 |
82 |
|
|
|
|
|
|
Total NJP |
486 |
903 |
|
308 |
541 |
|
|